Most first-time buyers imagine the custom process as a long conversation that ends with a container. In practice it is seven decisions with a fixed order, and the order is what protects both sides: each stage produces a document that the next stage depends on, and money moves only when a document is signed off.
This is the sequence we run on every custom build, with the approval points, what each stage costs you in time, and the four places where projects typically go wrong.
The seven stages, at a glance
| Stage | You provide | We produce | Money |
|---|---|---|---|
| 1. Brief | Species, size range, venue, opening date, budget band | Feasibility note and a size/motion option set | None |
| 2. Quotation | Confirmation of the option | Priced offer with the axis list and scope written out | None |
| 3. Drawings | Site plan, photos, power details | Dimensioned drawing, base and footing requirement | Deposit to start (40%) |
| 4. Sculpt approval | Sign-off or change list | Photos and video of the sculpt and pose before skin | Covered by deposit |
| 5. Build and test | Nothing, unless changes are requested | Motion test video per axis, paint to approved reference | — |
| 6. Pre-shipment inspection | Confirmation or a third-party inspector | Packing list, photos, serial numbers, documentation pack | Balance (60%) before packing |
| 7. Shipping and commissioning | Import clearance, site readiness | Freight, assembly drawings, remote or on-site commissioning | Freight per agreed terms |
Stage 1: the brief that saves a month
Four facts decide 80% of the design, and all four are yours to supply:
- Where it stands — indoor hall, fenced trail, roadside, rooftop. This sets build, IP rating and base design.
- How far away people stand — under 2 m, 3–8 m, over 15 m. This sets where the detail budget goes.
- When it must open — a fixed date changes the shipping mode and sometimes the size.
- What the number is — a real budget band, not “we will see”. Ten percent of the world’s animatronic projects fail at stage 3 because the drawing is finished before anyone realises the budget only covers a static piece.
Send photos of the site, even phone photos with a person standing where the model will go. Scale is judged from those faster than from any drawing.
Stage 2: reading the quotation properly
A quotation for a custom animal is only comparable if five things are written down. Ask for them explicitly:
| Item | Why it belongs in the offer |
|---|---|
| Axis list | Jaw, neck, forelimbs, tail, breathing, eyes — the list is the price |
| Drive type per axis | Pneumatic, DC or servo; a mix is normal on large models and should be stated |
| Skin and finish specification | Silicone layers, UV-stable pigment, flame-retardant additive |
| Scope boundary | Who does foundations, power, unloading, assembly, commissioning |
| Documentation | Drawings, wiring diagram, program backup, spare parts list |
If two offers differ by 30%, the axis list usually explains it before the price does.

Stage 3: drawings are the contract
Once the deposit is in, the build starts with a drawing set rather than steel. What you should receive:
- A dimensioned side and front elevation — body length, standing height, base footprint, and the pose drawn, not described.
- A base and footing requirement — point loads, anchor positions, concrete volume and bolt specification. This goes to your contractor, not into a drawer.
- A power requirement — connected load in kW, recommended breaker size, cable route and the position of the control cabinet.
- A shipping breakdown — how many pieces, crate dimensions, total volume and estimated weight.
Changes are cheapest here and most expensive after painting. If the pose is wrong, say so at this stage; a redraw costs a day, a rebuilt armature costs a month.
Stage 4: sculpt approval — the one approval not to rush
Before skin goes on, the foam sculpt exists and can still be changed with a knife. This is the only moment in the project when proportion and pose are cheap to fix, so ask for:
- Photos from four angles, in daylight, with a person or a known object for scale.
- A slow video walk-around, not a wide shot from one side.
- The head in close-up, since the head carries the species read.
Approve with a written list (“head 8% too large, jaw angle closed by 10°”), not with “looks good”. Written changes get implemented; impressions get interpreted.
Stage 5: build, motion test and the baseline video
Assembly and programming take the longest block of the schedule. Two things you should receive before anyone talks about shipping:
- A motion test video per axis, with the serial number visible in frame. This is your baseline: it proves what the model did before it left, and it is the reference for “normal” when a joint sounds different in year three.
- Paint reference photos next to the approved colour reference, in daylight. Screens lie about colour; daylight photos do not.
This is also when the documentation pack is produced: wiring diagram, parameter backup, spare parts list. Chase it here, because after the balance is paid the paperwork has a habit of arriving late.

Stage 6: pre-shipment inspection
The balance is normally due once the goods are finished and confirmed, before packing. Before you confirm, check:
| Check | How |
|---|---|
| Every axis moves through its full range | Live video call, not a pre-recorded clip |
| Paint matches the approved reference | Daylight photos beside the reference swatch |
| Skin has no seam gaps at flex points | Close-up photos of shoulder, hip, jaw |
| Packing is export-grade | Photos of crate walls, foam blocking, steel strapping |
| Documentation complete | Digital copies received, not promised |
| Spares present | Itemised list photographed inside the crate |
If you want a third-party inspector, book them at this stage; inspectors who arrive after packing can only confirm what the packing list says.
Stage 7: shipping, site readiness and commissioning
Most delay at this stage is on site, not at sea. The five things that should be finished before the container lands:
- Footings poured and cured — concrete needs 7 days minimum before anchors are loaded, 28 to full strength.
- Power run to the position with the breaker installed and labelled.
- Access route clear — gate width, turning circle, ground bearing for the delivery vehicle.
- Unloading equipment booked — forklift or crane sized to the heaviest section.
- Two staff released for commissioning, the same two who will run the model afterwards.
Commissioning itself is a sequence: base, frame, skin panels, cables, program, then a full cycle with the operator. For a 4–6 m model with four to six axes, plan half a day to two days per unit including briefing.
The four places projects go wrong
- Approving a sculpt from one photo. Proportion errors survive a single angle. Ask for four.
- Leaving the foundation to “whoever is on site”. The footing drawing exists for a reason; a pad sized by guesswork is the most common cause of a model that later leans.
- Changing the pose after paint. Cheapest at stage 3, brutal at stage 5.
- Not attending the motion test. Fifteen minutes on a video call at the factory saves a week of remote diagnosis after arrival.
Frequently asked questions
How long does a custom build take?
There is no fixed lead time; it depends on size, axis count and the workshop schedule, and peak season is longer. What matters is that the milestone dates — drawings, sculpt approval, test, packing — are agreed at order, because each one is a decision you have to make, not a step the factory can absorb.
How much deposit is normal?
40% to start production, with the 60% balance payable once the finished goods are confirmed and before packing. Payment is by T/T against a proforma invoice with the company bank details.
Can we change the design mid-build?
Before sculpt approval, freely. Between sculpt and paint, with cost and a schedule impact. After painting, only if the change is worth rebuilding — and at that point it is usually better to add a second model than to alter the first.
Do you install on site?
For larger projects and models above 8 m we can send an installation team; costs are covered by the client. For smaller units we supply assembly drawings, labelled parts, manuals and video guidance, plus remote support during installation. Both routes are normal, and the choice is usually made on labour cost at your end rather than on difficulty.
What happens if something arrives damaged?
Photograph the crate before opening, then the damage, then the packing around it. Claims depend on that sequence, and shipping insurance depends on it too. Report within the claim window stated in the offer, and keep the packaging until the claim is settled.
If you have a site and a species in mind, send both and we will come back with a feasibility note and a size option set before any money moves. Start a project brief, or look at the installed projects for what these stages produce.


